Pallion Engineering

Mar 2019

Rovin Environmental was awarded the Asbestos removal phase as part of a major refurbishment project at the Pallion Engineering shipyard. The works were employed under fully controlled conditions to ensure the safe removal of asbestos insulating board panels to the dividing wall of the warehouses. The impressive enclosure was constructed from 480 8ft timber frames covering a total area of 840m3. Battery operated Scissor lifts were used for the initial enclosure setup including the internal removal works, our anticipated time duration of four weeks was achieved, safely, within budget and to the highest of standards.